Update on the Island development and Dam development

Regarding the Dam project and according to the Hugo City Council Meeting of Nov 3rd:

  1. Total project cost = $640K
  2. Grant received from MNDOT = $252K
  3. MN DNR has agreed to a grant = $160K
  4. Remaining cost of $228K to be split between the RCWD and Hugo.
  5. RCWD has committed to $113K.
  6. Hugo to attempt to get funding from St Paul Water Utility and communities surrounding the lake.
  7. This was approved by the Hugo City Council at this meeting.
So, that's great news.  I suspect that we will see construction begin after the water goes down next spring.  It is probably too optimistic to think that it will take place this winter.  Time will tell.

Island project
The island project has been approved by the Township board.  It will now move to the planning commission for further discussions and approvals.  The White Bear Press has an article in today's paper on the meeting and decision.